Bond 2023
Bond Updates
Updated sound systems in all elementary classrooms and new staff MacBooks are among the first group of technology purchases from the 2023 bond.
Building Projects
- Dooley Center
- Disney Elementary
- Edison Elementary
- Eisenhower Elementary
- Emerson Elementary
- Salk Elementary
- Twain Elementary
- Richards Middle
- Fraser High
- Admin Building
- Operations Building
- Transportation Building
Dooley Center
$1.82 million in proposed projects
Year Built: 1965
- Safety & Security
- Replace cafeteria doors, frames, and hardware
- Replace select exterior doors
- Upgrade interior lighting (LED)
- Replace PA system speakers
- Replace all exit signs
- Mechanical/Electrical Work
- Replace unit vents
- Replace rooftop unit
- Replace the central air handling unit and condensing unit
- Add valves to piping systems
- Rebuild existing boilers
- Technology Improvements
- Update network infrastructure
- Purchase audio-visual systems and instructional devices
- Furniture and Equipment
- Purchase custodial equipment
- Site Work
- Replace 45,000 sq ft of asphalt paving
- Replace 4,500 sq ft of concrete sidewalks
Disney Elementary
$3.54 million in proposed projects
Year Built: 1958
- Exterior Work
- Total roof replacement
- Safety & Security
- Replace select exterior doors and frames
- Add security cameras
- Replace classroom blinds on exterior windows
- Upgrade interior lighting (LED)
- Replace non-LED exterior lighting
- Replace PA system speakers
- Add access control at select exterior doors
- Replace all exit signs
- Mechanical/Electrical Work
- Replace classroom unit vents
- Replace rooftop units
- Replace boiler, pumps, valves, and piping
- Technology Improvements
- Update network infrastructure
- Purchase audio-visual systems and student iPads
- Furniture and Equipment
- Purchase custodial equipment
- Site Work
- Replace 45,000 sq ft of asphalt paving
- Replace 4,500 sq ft of concrete sidewalks
Edison Elementary
$3.71 million in proposed projects
Year Built: 1960
- Exterior Work
- Install a new roof at the 2005 building addition
- Safety & Security
- Replace select exterior doors and frames
- Add security cameras
- Replace classroom blinds on exterior windows
- Upgrade interior lighting (LED)
- Replace PA system speakers
- Add access control at select exterior doors
- Replace all exit signs
- Mechanical/Electrical Work
- Replace classroom unit vents
- Replace rooftop units
- Replace pumps, valves, and piping
- Rebuild existing boiler
- Technology Improvements
- Update network infrastructure
- Purchase audio-visual systems and student iPads
- Furniture and Equipment
- Purchase custodial equipment
- Site Work
- Replace 45,000 sq ft of asphalt paving
- Replace 4,500 sq ft of concrete sidewalks
Eisenhower Elementary
$4.17 million in proposed projects
Year Built: 1957
- Exterior Work
- Install a new roof at the 2005 building addition
- Safety & Security
- Replace select exterior doors and frames
- Add security cameras
- Replace classroom blinds on exterior windows
- Upgrade interior lighting (LED)
- Replace PA system speakers
- Add access control at select exterior doors
- Replace all exit signs
- Mechanical/Electrical Work
- Replace classroom unit vents
- Replace rooftop units
- Replace boiler, pumps, fittings, and piping
- Technology Improvements
- Update network infrastructure
- Purchase audio-visual systems and student iPads
- Furniture and Equipment
- Purchase custodial equipment
- Site Work
- Replace 45,000 sq ft of asphalt paving
- Replace 4,500 sq ft of concrete sidewalks
Emerson Elementary
$3.45 million in proposed projects
Year Built: 1965
- Exterior Work
- Total roof replacement
- Safety & Security
- Replace select exterior doors and frames
- Add security cameras
- Replace classroom blinds on exterior windows
- Upgrade interior lighting (LED)
- Replace exterior light poles/heads
- Replace non-LED exterior lighting
- Replace PA system speakers
- Add access control at select exterior doors
- Replace all exit signs
- Mechanical/Electrical Work
- Replace rooftop units
- Replace boiler pumps, valves, and piping
- Technology Improvements
- Update network infrastructure
- Purchase audio-visual systems and student iPads
- Furniture and Equipment
- Purchase custodial equipment
- Site Work
- Replace 45,000 sq ft of asphalt paving
- Replace 4,500 sq ft of concrete sidewalks
Salk Elementary
$4.49 million in proposed projects
Year Built: 1960
- Exterior Work
- Install a new roof at the 2005 building addition
- Safety & Security
- Replace select exterior doors and frames
- Replace exterior gym doors
- Add security cameras
- Replace classroom blinds on exterior windows
- Upgrade interior lighting (LED)
- Replace PA system speakers
- Add access control at select exterior doors
- Replace all exit signs
- Mechanical/Electrical Work
- Replace classroom unit vents
- Replace rooftop units
- Replace fan coil units
- Add pumps, valves, and piping
- Rebuild existing boilers
- Technology Improvements
- Update network infrastructure
- Purchase audio-visual systems and student iPads
- Furniture and Equipment
- Purchase custodial equipment
- Site Work
- Replace 74,000 sq ft of asphalt paving
- Replace 4,500 sq ft of concrete sidewalks
Twain Elementary
$4.16 million in proposed projects
Year Built: 1960
- Exterior Work
- Replace entire roof
- Safety & Security
- Replace select exterior doors and frames
- Replace exterior gym doors
- Add security cameras
- Replace classroom blinds on exterior windows
- Upgrade interior lighting (LED)
- Replace non-LED exterior lighting
- Replace PA system speakers
- Add access control at select exterior doors
- Replace all exit signs
- Mechanical/Electrical Work
- Replace classroom unit vents
- Replace rooftop units
- Replace fan coil units, and piping values
- Rebuild existing boilers
- Technology Improvements
- Update network infrastructure
- Purchase audio-visual systems and student iPads
- Furniture and Equipment
- Purchase custodial equipment
- Site Work
- Replace 70,000 sq ft of asphalt paving
- Replace 4,500 sq ft of concrete sidewalks
Richards Middle
$10.42 million in proposed projects
Year Built: 1969
- Exterior Work
- Install a new roof on the gym and flat roofs
- Replace flashing of roof gables
- Safety & Security
- Replace select exterior doors and frames
- Add security cameras to the facility and stadium
- Add audio-visual systems to the gym
- Update the gym windows and walls
- Upgrade interior lighting
- Replace non-LED exterior lighting
- Add access control at select exterior doors
- Replace all exit signs
- Mechanical/Electrical Work
- Replace CTE rooftop unit
- Add valves to piping systems
- Replace pipe connection fittings
- Replace temperature controls
- Rebuild existing boilers
- Replace water heaters
- Replace chillers
- Replace air handling units
- Replace ceiling-mounted unit vents
- Technology Improvements
- Update network infrastructure
- Purchase audio-visual systems and student MacBooks
- Furniture and Equipment
- Purchase custodial equipment
- Site Work
- Replace 85,000 sq ft of asphalt paving
- Replace 10,000 sq ft of concrete sidewalks
- Site work to replace the chiller (screen wall, doors, and concrete)
Fraser High
$21.23 million in proposed projects
Year Built: 1970
- New Construction
- Expand the athletic support facility at the stadium
- Exterior Work
- Install a new roof at the 2005 building additions
- Update exterior finishes (insulation and metal panels)
- Add storage to existing stadium building
- Safety & Security
- Replace select exterior doors and frames
- Update auxiliary gym floor
- Add security cameras
- Replace non-LED exterior lighting
- Upgrade main and auxiliary gym lighting to LED
- Replace PA system speakers
- Add access control at select exterior doors
- Replace all exit signs
- Mechanical/Electrical Work
- Upgrade the auditorium control board and sound equipment
- Replace boiler plant, pumps, and piping
- Replace water heaters
- Replace chiller plant components
- Replace pool heater
- Replace unit vents in classrooms
- Replace rooftop units
- Replace air handling units
- Add valves to piping systems
- Replace pipe connection fittings
- Technology Improvements
- Update network infrastructure
- Purchase audio-visual systems and student MacBooks
- Furniture and Equipment
- Purchase custodial equipment
- Site Work
- Replace the west parking lot
- Replace the east parking lot
- Replace the asphalt at the south lot
- Replace concrete
- Improve stormwater management
Admin Building
$778 thousand in proposed projects
Year Built: 1972
- Exterior Work
- Reconstruct and waterproof below-grade wall
- Safety & Security
- Upgrade interior lighting (LED)
- Mechanical/Electrical Work
- Replace boiler plant, pumps, and piping
- Technology Improvements
- Update network infrastructure
- Site Work
- Replace 23,000 sq ft of asphalt paving
- Replace 2,500 sq ft of concrete sidewalks
Operations Building
Transportation Building
$491 thousand in proposed projects
Year Built: 1968
- Exterior Work
- Replace roof
- Replace storefront window
- Safety & Security
- Add access control at select exterior doors.
- Upgrade interior lighting (LED)
- Add access control at select exterior doors
- Technology Improvements
- Update network infrastructure
- Equipment
- Purchase three buses
- Site Work
- Replace 25,000 sq ft of asphalt paving
- Replace 2,500 sq ft of concrete sidewalks
- Replace 460 sq ft of fencing